Home » Services » Case Studies » Case Study: Supply Sea Defence Timbers – Eastbourne Beach
Sector: Marine
Eastbourne contract was scheduled to last 18months. As the Environmental Agency released more money in small amounts G&A had to draw down stock to keep Employees & Equipment on site. G&A were delivering 8 lorry loads a month from its stock in Scotland.
TIMESCALES:
Contract length was 3 years. Regular and consistent supply was critical and was maintained throughout.
TIMBER REQUIREMENTS:
VALUE ADDED: